Professional Documents
Culture Documents
ISSN No:-2456-2165
Abstract:- Productivity is an essential element in 88% (ratio 1 and 2) and 75% (ratio 5). The five why
achieving good production competitiveness. Companies analysis of the three ratios shows four root causes of the
need to know where their productivity levels are. low productivity score of ratio 1, ratio 2, and ratio 5.
Productivity measurement is instrumental at the After further research with the 5W+1H method, it was
management level in doing strategic planning. Objective found that recommendations for improvement that can
Matrix (OMAX) is a partial productivity measurement be done are to increase the supervisory function in
system used to monitor Productivity in each part of the production, updating SOPs, conducting job evaluations
company with productivity criteria according to the and training, as well as scheduling machine
existence of that part (Objective). The measurement of maintenance.
Productivity using the OMAX method also involves the
AHP method in determining the weight of each ratio. Keywords:- Objective Matrix, OMAX, Analytic Hierarchy
Based on the calculation of Productivity in the period Process, Traffic Light System, Why why Analysis, 5W + 1H
January - August 2020 using the Objective Matrix
Method, the results obtained that the productivity values I. INTRODUCTION
below the average productivity values are the period in
March (-15%), April (-39%), May (-1%) and July (- Research at PT Tiga Bintang Gautama was conducted
65%) 2020. Then from the results of calculations with because of indications of a decline in competitiveness in its
OMAX for the period January-August 2020, the production capabilities. During the observation process, it
achievement scores of each ratio were analyzed using the was found that there were issues related to inadequate
TLS method and calculated the index of achievement Productivity. According to data from PT Tiga Bintang
scores against standard productivity scores. The Gautama's monthly production data during the January -
calculation results show that three ratios get a score August 2020 period, it was found that the ongoing
below the standard. Ratio 1, Ratio 2, and Ratio 5 get an production process could not keep up with the demand for
index of achievement score against the standard score of orders and targets given by the company.
Table 1 Monthly Production Data of PT Tiga Bintang Gautama for the period January – August 2020 (in kg)
Purchase Order 15800 16100 16500 14600 15900 15300 15700 15900 15725
Production Targets* 16830 17380 17710 18150 16060 17490 16830 17270 17215
Actual Production 13040 13240 12700 12540 12480 12900 12240 11990 12641.3
The data above shows that during the period January - Why Analysis method. Which will also be followed up with
August 2020, the Production line of PT Tiga Bintang an analysis of problem fixes using the 5W + 1H method.
Gautama could not achieve the production target for each
period. This condition makes the competitiveness of PT II. LITERATURE REVIEW
Tiga Bintang Gautama very low. Calculation of Productivity
is one of the efforts to evaluate the performance of the Understanding Productivity according to Daryanto
production line. The Objective Matrix method is used as a (2012:41), Productivity is a concept that describes the
calculation method because the object studied is only in the relationship between results and sources to produce these
production section. The AHP method is also used as a tool results. Objective Matrix (OMAX) is a partial productivity
to determine the weight of each ratio. And then be further measurement system used to observe Productivity in each
analyzed to determine the cause of the problem with the 5 part of the company with criteria or productivity ratios
following the existence of that part (Objective). This method
After the results of the OMAX standard table Actual Product Quantity (kg)
calculation are complete, the value of each period is entered Ratio 4 : Electrical energy (kWH)
one by one to find the total productivity score for each
period. After that, a performance index is obtained for each b) Effectiveness Criteria
period which shows a surplus or minus from the standard
performance value. The next stage is to analyze further the Actual Product Quantity (kg)
Ratio 5 :
ratios that have the most impact on the low value of total Production Target (kg)
Productivity. The TLS method is used by making a score
Defect Product (kg)
table for each ratio throughout the period studied. Ratios that Ratio 6 :
Actual Product Quantity (kg)
fall into the red zone throughout the period and have a score
After that, calculate the interval scale to fill in scores 1 and 2 Skor 10 − Skor 4
Interval Scale : 7
with the following formula.
Skor 3 − Skor 0 n score : Score n-1 + Interval Scale
Interval Scale :
3
After that, determine the weight of each ratio in the
n score : Score n-1 + Interval Scale OMAX matrix. In determining the weight of each ratio, the
emphasis is on determining the priority value of the criteria,
Then calculate the interval scale to fill in a score of 4 to 9 namely comparing which one is more important between
with the following formula. one criterion and another. The AHP method was used with
the following results.
Ratio 2 (PA/JTK) 0.201 0.201 0.296 0.226 0.137 0.082 0.171 19%
Ratio 3 (PA/BB) 0.067 0.067 0.099 0.338 0.137 0.082 0.171 14%
Ratio 4 (PA/EL) 0.100 0.100 0.099 0.113 0.410 0.245 0.122 17%
Ratio 5 (PA/TP) 0.201 0.201 0.099 0.038 0.137 0.408 0.220 19%
Ratio 6 (PC/PA) 0.201 0.201 0.099 0.038 0.027 0.082 0.122 11%
After getting the results of the weight of each ratio, then entered into the OMAX standard table.
Based on the results of the productivity calculation using the Objective Matrix method, the productivity value for the
January-Aug 2020 period is obtained. Then the productivity index is calculated by comparing the performance indicators for each
period with the basic period.
The table above shows that from the calculations using the OMAX method, there was a decrease in below-standard
Productivity in March, April, May, and July 2020. A negative value indicates it in the productivity index.
With the help of the TLS method in the table above, it three ratios have below standard achievements. Thus, these
is easy to identify the ratios that require immediate three ratios will be analyzed for causes and
improvement. Among them are ratio 1, ratio 2, and ratio 5, recommendations for improvement.
where the three ratios have no scores in the green zone.
Root Cause Analysis (Five Whys Analysis)
The percentage of achievement of the total score of Of the three ratios that have scores below the standard,
each ratio to the basic score of each ratio also shows that the root cause analysis uses the 5 Whys Analysis method.
The efficiency of
There is no There is no
the Number of Cooperation in Lack of workers
SOP is not going written SOP that written SOP that
Ratio 2 Labor against the work is not understanding of
well is clear and easy is clear and easy
amount of Actual efficient efficient work
to understand to understand
Production is low
No job
Unproductive No job evaluation
evaluation and
workers and training
Actual Production training
Low Actual
Effectiveness The machine
Ratio 5 Production
against Low cannot reach the Maintenance Maintenance
Achievement
Production Target required machine not machine not
production noticed noticed
capacity
Table 10 5W+1H
Items Root Cause What Why Where when Who How
The
The Production
Production
Supervisor
Supervisor The production
does not carry Carry out the
does not supervisor does not
out the supervisory function
Ratio carry out the understand his Dep. 2021 Spv
supervisory properly so that
1 supervisory obligations in carrying Production period production
function in a production continues
role in a out the supervisory
strict and to run optimally.
tough and function.
disciplined
disciplined
manner.
manner.
SOP has never been
It updates the SOP
There is no There is no updated in the last few
with a language that is
written SOP written SOP years and has not
Ratio Dep. 2021 Kep easier to understand
that is clearly that is clearly made posters or
2 Production period Production and makes a printed
and easily and easily pamphlets that the
version to be pasted in
understood. understood. operator can read at
the production area.
any time.
They are conducting
job evaluations and
There is no Workers are only training on effective
There is no job Head of
job trained during their Dep. 2021 and efficient work
evaluation and the
evaluation training period, which Production period methods and
training. production
and training. is the first month. providing Industrial
Ratio K3.
5
Because not realizing Perform the most
The Machine that downtime and effective and efficient
Head of
maintenance maintenance decreased machine Dep. 2021 maintenance
the
engine is not is not performance make a Production period scheduling on the
production
noticed. considered. significant impact on current production
Productivity. scheme.
V. CONCLUSION AND SUGGESTION the 5 Whys Analysis method. The root cause of the
three ratios is obtained as follows.
Conclusion a. Ratio 1 - The Production Supervisor does not carry out
Based on the calculations and analysis of production the supervisory function strictly and is disciplined.
line productivity at PT Tiga Bintang Gautama in this study, b. Ratio 2 - There is no written SOP that is clearly and
the following conclusions were obtained. easily understood.
1. Based on the calculation of Productivity in the period c. Ratio 5 - No job evaluation and training.
January - August 2020 using the Objective Matrix d. Ratio 5 - Machine maintenance is not noticed.
Method, the results obtained that productivity values
below the average productivity values are the periods in And from the four root causes, The improvement
March (-15%), April (-39%), May (-1%) and July (-65 recommendation analysis was carried out using the 5W +
%) 2020. 1H method with the following recommendations for
2. From the results of calculations with OMAX for the
improvement.
period January-August 2020, the achievement of scores
for each ratio using the TLS method was analyzed, and
a. We are maximizing the Supervisory function in the
the index of achievement scores against standard
productivity scores was calculated. The results of the organizational system.
b. It updates the SOP with a language that is easier to
analysis show that three ratios get scores below the
standard. Ratio 1, Ratio 2, and Ratio 5 get a score understand and makes a printed version to be pasted in
achievement index to the standard score of 88% (ratio 1 the production area.
and 2) and 75% (ratio 5). c. We are conducting job evaluations and training on
3. Of the three ratios that get a total score below the effective and efficient work methods and providing
Industrial K3.
standard total score, a cause analysis is carried out using