Professional Documents
Culture Documents
ISSN No:-2456-2165
Abstract:- Over the years, there have been ineffective Estimating of quantities and cost in building and civil
and inaccurate results being noticed to have been gotten engineering works is a very complex task to undergo,
over time when bill of civil and engineering quantities are because it requires a careful and full understanding of the
computed manually. However, with the aid of a construction methods and construction materials to get a
developed software package in calculating the bill of reasonable forecast due to the uncertainty in the price of item
quantities, effective and efficient results would be gotten. to be used for a construction project as a result of
From the foregoing this study aims at developing a environmental change, change in political environment,
computer aided model to digitally compute building and price trend as well as change in technological demand of
civil engineering quantities using C# programming goods and services, estimating of quantities and cost of
language. The approach used in this study is developing construction work as proven to be very complex, full of
the digital computation program and testing the errors and time consuming (Oluyemi, 2016). These days,
computational program using the manual taking off Information and Communication Technology (ICT) is
from both residential building and road plans to validate responsible for the entire construction process from
the software. The results obtained from this study information being generated, transmitted and interpreted
indicate that, with reference to the residential building to enabling the project to be built, maintained and eventually
plan, 100% of the substructure items found in the bill fall recycled (Ikechukwu et al.,2011). Although communication
within 0 to 0.05 percentage difference and 75% of the is an essential value in construction projects, the construction
superstructure items have 0 to 0.4 percentage industry is confronted with the importance and use of
differences. In road plan, 100% of the items in site information and communication technology (ICT). As most
clearing and earthworks (Bill no. 2) have 0 percentage firms in developed countries have increased and will
differences, while 86% of the items in bill no. 3 ( increase further their investment in ICT, this has raised
drainage and culverts) have 0 percentage differences. productivity within their construction industry and resulted
All items in bill no.4 (Pavement and surfacing) have 0 in an increase in the quality and speed of work, financial
percentage differences between the manual and digital controls, communications, and access to common data.
computation. Since there are little or no difference in Firms in the third world countries are yet to understand this
the result obtained from manual computation and essential value and its importance to the development of their
digital computation. Therefore, the developed digital construction sector (Ikechukwu et al., 2011).
computation program is efficient and reliable and can be
used in lieu of the manual estimation. This study aims to develop application software by
using C# programming language for the measurement and
I. INTRODUCTION quantification of building and civil engineering works by
validating the software and comparing the results with
The recent development in the computer field, and the manual computation.
evolution of powerful and affordable microcomputers which
now out-perform old minicomputers have created great II. AIM AND OBJECTIVES
potential for their use in the building and civil engineering
industries. Computing is a very essential application in our The aim of this research is to develop application
day-to-day activity. Also, computing has come a long way software for the measurement and quantification of building
in enhancing excellent results in engineering applications. and civil engineering works.
Introducing the concept of computing to all professions has The objectives are to:
been a tremendous step in ensuring effective output/results review the concept of quantity estimation.
for every input. In addition, the proliferation of construction develop application software using Microsoft Visual
related software has resulted in the development of more SEE-SHARP (C#) programming language for digital
efficient decision support systems for the management of computation and
both the construction company and its construction sites. evaluate the software for suitability, reliability and
recommend accordingly.
Fig 5: A Flow Chart Diagram Illustrating step by step process of the Building Program
Table 1: Draft Bill Obtained From the Manual Computation of the Proposed Building
SUBSTRUCTURE
ITEM DESCRIPTION QUANTITY UNIT
A Site Clearing 229.00 m2
B Top Soil Removal 183.30 m2
C Trench Excavation 88.20 m3
D Level and Ram 73.49 m2
E Foundation Blinding 73.49 m2
F Foundation Concrete 16.91 m2
G Foundation Block work 129.70 m2
H Backfilling 49.72 m3
I Cart away 79.98 m3
J Laterite Filling 43.35 m3
K Hardcore 43.35 m
L DPM and BRC Mesh 73.50 m2
M Formwork for Oversite 54.00 m2
N Concrete Slab 25.60 m3
SUPERSTRUCTURE
ITEM DESCRIPTION QUANTITY UNIT
A Block wall 225.00 m2
B Lintel Concrete 2.25 m3
C Formwork for Lintel 9.94 kg
D Reinforcement 388.40 kg
Table 2: Draft Bill Obtained from the Digital Computation of the Proposed Building
SUBSTRUCTURE
ITEM DESCRIPTION QUANTITY UNIT
A Site Clearing 229.00 m2
B Top Soil Removal 183.30 m2
C Trench Excavation 88.00 m3
D Level and Ram 73.40 m2
E Foundation Blinding 73.40 m2
F Foundation Concrete 73.40 m2
G Foundation Block Wall 129.70 m2
H Backfilling 50.00 m3
I Cart away 79.98 m3
J Laterite Filling 43.35 m3
K Hardcore 43.35 m
L DPM and BRC Mesh 73.50 m2
M Formwork for Oversite 54.00 m2
N Concrete Slab 26.00 m3
Table 3: Comparison of Draft Bill Results for the Proposed 3-bedroom flat at Oba Ile, Akure, Ondo State.
SUBSTRUCTURE
MANUAL DIGITAL
COMPUTATION COMPUTATION
ITEM DESCRIPTION QANTITY/UNIT QUANTITY/UNIT DIFFERENCE % DIFFERENCE
A Site Clearing 229.00 m2 229.00 m2 0.00 0.00
B Topsoil Removal 183.30 m2 183.30 m2 0.00 0.00
C Trench Excavation 88.20 m3 88.22 m3 0.02 0.02
D Level and Ram 73.40 m2 73.40 m2 0.00 0.00
E Foundation Blinding 73.40 m2 73.40 m2 0.00 0.00
F Foundation Concrete 73.40 m2 73.40 m2 0.00 0.00
G Foundation Block work 129.70 m2 129.70 m2 0.00 0.00
H Backfilling 49.72 m3 49.73 m3 0.01 0.02
I Cart away 79.98 m3 79.98 m3 0.00 0.00
J Laterite Filling 43.35 m3 43.35 m3 0.00 0.00
K Hardcore 43.35 m 43.35 m 0.00 0.00
L DPM and BRC Mesh 73.50 m2 73.50 m2 0.00 0.00
M Formwork for Oversite 54.00 m2 54.00 m2 0.00 0.00
N Concrete Slab 25.60 m3 25.60 m3 0.00 0.00
SUPERSTRUCTURE
MANUAL DIGITAL
COMPUTATION COMPUTATION
ITEM DESCRIPTION QUANTITY/UNIT QUANTITY/UNIT DIFFERENCE % DIFFERENCE
A Block wall 225.00 m2 225.00 m2 0.00 0.00
3
B Concrete in Lintel 2.25 m 2.20 m3 0.05 2.27
C Formwork for Lintel 9.94 kg 9.90 kg 0.04 0.40
D Reinforcement (12mm) 388.40 kg 388.40 kg 0.00 0.00
The result shown in table 3 can be summarized as dynamically interactive. The application has the capability
follows; to accept, run, perform, execute and give the final answers to
numerical iteration method adopted, thereby computing
Substructure- 100% of the 14 items found in this quantities and costs.
bill fall within 0 to 0.05 percentage difference.
The results obtained indicate that substructure has
Superstructure- 75% of the items has 0 to 0.4 100% of the 14 items found in this bill falls within 0 to 0.05
percentage difference. From the summary above, the result percentage difference, Superstructure 75% of the items have
shows that there are little or no difference in the final outputs 0 to 0.4 percentage difference. Also, from Bill no.2, site
of the quantities obtained through the manual clearing and earthworks, 100 percent of the items in this bill
computation and the digital computation for the project. have 0 percentage difference, Bill no.3 drainage, 86% of
Therefore, the developed digital estimation program can the items in this bill has 0 percentage difference and 14%
be said to be efficient and accurate in its final outputs and has 1.354 percentage differences in it.
can be used in place of manual computation with its other
advantages. Therefore, it is recommended to use the application
software developed using a combination of Microsoft visual
V. CONCLUSION AND RECOMMENDATION C SHARP (C# version 2012) and Microsoft visual studio
Environment (version 2012) as it is proven to have the
The development of the software was achieved using a following:
combination of good programming Microsoft visual C The developed program will solve the problem of fatigue
SHARP (C# version 2012) and Microsoft visual studio and limit potential errors in quantity estimation and bill
Environment (version 2012), which allows an artistic preparation as well as reduce the time consumed.
application to be created, visually appealing and The program was designed in such a way that the users